Below and attached, you will find the status reports for Phases 1A and 1B of the St. Landry Parish Smooth Ride Home rural road improvement program. This project is funded through a 15-year, two-cent sales tax in the rural portions of the parish with the funds dedicated exclusively to rural road improvements
.
Please contact Bill Fontenot, St. Landry Parish President, if you have questions or require additional information. 337-948-3688 w, 337-280-8982
Thank you. STATUS REPORT FOR PHASE 1A:
Project is approximately 85% complete. Shoulder material has been placed on most roads where asphalt work has been completed. All soil cement and 95% of drainage work is complete. Due to weather, little progress has been made over past several months. Some dress up work on roads that have been paved is taking place when weather permits and will continue. Roads remaining to be completed with asphalt surfacing include Hidden Hills (approximately 1250 l.f.), Oscar Rivette and Meche roads (which are approximately 50% complete), Don Guilbeau, Begnaud, Chretien Point, Jessie Richard and Osage Trail Roads. Due to weather, contractor has only been able to get 1-3 days of work in most weeks. With good weather conditions, I estimate approximately 3-4 weeks to complete asphalt work, with shoulders and dress up work to follow.
- K. Bill Fontenot, Jr., St. Landry Parish President
STATUS REPORT FOR PHASE 1B:
Smooth Ride Home Contract 1B is now approximately 70% complete. Based on present production I’m not anticipating completion until Late July/ Early Early August. Below is a summary of what’s complete.
1) WPA Road Complete other than striping and pavement marking
2) Cosay Rd Complete
3) Pointe Verte Complete
4) True Vine Complete
5) St Peters Complete
6) Rideau Rd Complete
7) Barnes Lane Complete
8) Bolden Rd Complete
9) Texas Eastern HMA complete aggregate shoulder material remaining
10) Dupre Rd HMA complete aggregate shoulder material remaining
11) Ross Rd HMA complete aggregate shoulder material remaining
12) Sage Rd HMA complete aggregate shoulder material remaining
13) St Mathew Rd HMA complete aggregate shoulder material remaining
14) St Berchman HMA complete aggregate shoulder material remaining
15) Frank Rd HMA complete aggregate shoulder material remaining
16) Chanterberry Rd HMA complete aggregate shoulder material remaining
17) Fontenot Rd HMA complete aggregate shoulder material remaining
18) Boudreaux St Soil cement cut
19) Deblieux St Soil cement cut
20) School Rd Soil cement cut
21) Duplechin Rd Soil cement cut
22) Babineaux Rd Soil cement cut
23) Noel Rd Culvert installation and soil cement in progress