Below and attached, you will find the status reports for Phases 1A and 1B of the St. Landry Parish Smooth Ride Home rural road improvement program. This project is funded through a 15-year, two-cent sales tax in the rural portions of the parish with the funds dedicated exclusively to rural road improvements

.

Please contact Bill Fontenot, St. Landry Parish President, if you have questions or require additional information. 337-948-3688 w, 337-280-8982

Thank you.  STATUS REPORT FOR PHASE 1A:

Project is approximately 85% complete.  Shoulder material has been placed on most roads where asphalt work has been completed.  All soil cement and 95% of drainage work is complete.  Due to weather, little progress has been made over past several months.  Some dress up work on roads that have been paved is taking place when weather permits and will continue.  Roads remaining to be completed with asphalt surfacing include Hidden Hills (approximately 1250 l.f.), Oscar Rivette and Meche roads (which are approximately 50% complete), Don Guilbeau, Begnaud, Chretien Point, Jessie Richard and Osage Trail Roads.   Due to weather, contractor has only been able to get 1-3 days of work in most weeks.  With good weather conditions, I estimate approximately 3-4 weeks to complete asphalt work, with shoulders and dress up work to follow.

  1. K. Bill Fontenot, Jr., St. Landry Parish President

STATUS REPORT FOR PHASE 1B:

Smooth Ride Home Contract 1B is now approximately 70% complete. Based on present production I’m not anticipating completion until Late July/ Early Early August. Below is a summary of what’s complete.

1)      WPA Road              Complete other than striping and pavement marking

2)      Cosay Rd                 Complete

3)      Pointe Verte           Complete

4)      True Vine                Complete

5)      St Peters                  Complete

6)      Rideau Rd                Complete

7)      Barnes Lane            Complete

8)      Bolden Rd                Complete

9)      Texas Eastern         HMA complete aggregate shoulder material remaining

10)   Dupre Rd                  HMA complete aggregate shoulder material remaining

11)   Ross Rd                     HMA complete aggregate shoulder material remaining

12)   Sage Rd                     HMA complete aggregate shoulder material remaining

13)   St Mathew Rd         HMA complete aggregate shoulder material remaining

14)   St Berchman            HMA complete aggregate shoulder material remaining

15)   Frank Rd                   HMA complete aggregate shoulder material remaining

16)   Chanterberry Rd     HMA complete aggregate shoulder material remaining

17)   Fontenot Rd             HMA complete aggregate shoulder material remaining

18)   Boudreaux St           Soil cement cut

19)   Deblieux St               Soil cement cut

20)   School Rd                  Soil cement cut

21)   Duplechin Rd            Soil cement cut

22)   Babineaux Rd           Soil cement cut

23)   Noel Rd                     Culvert installation and soil cement in progress